1、国际工程管理实务与翻译(08-09)作业实用翻译价格清单中的固定总价和单价应被视为包括标书和合同文件中所述的全部工作,合同项下所述的工作实施和承包商义务履行所需的服务及其他工作,无论此清单中详细描述与否。Fixedpriceandunitpriceinthepricelistshalldetaillistsofallitemsofworkspecifiedinthetenderandthecontract,worksexecutionrequiredtobecarriedoutinthecontract,servicesneed
2、edtofulfillthecontractor’sobligationandotherworks,whethergivingadetaildescriptioninthepricelistornot.所有与本工程项目有关的针对承包商的或业主要求承包商缴纳的税金、保险费,以及政府和非政府部门征收的各种费用。除另有说明外,所填写的单价将被认为已包含一切执行及完成该项目所须的费用,包括材料、人工、搬运、储存、裁切、耗损、吊运、定位、安装、包装、工具、器械、折旧,辅助人工和材料以及辅助措施,营业费、税务、开办费、行政支援、利润、分段执
3、行、检验检测、验收、返工、加班、恶劣气候条件的防护保证措施、清洁清理、成品保护、保险、政府部门应收费用等等所有相关的费用。Theunitpriceofallthetaxes,insurance,andexpensesleviedbythegovernmentandnon-governmentsector,whichareconsistentwithContractor’sobligationrelevanttotheworksorrequiredbytheemployer,shallbedeemedtocoveralltheex
4、pensesneededintheexecutionandcompletionofworks,unlessotherwisestated,includingmaterials,manualwork,transport,storage,cropping,wastage,swing,location,erection,tools,instruments,depreciation,auxiliarymanpowerandmaterials,supportmeasures,operatingexpenses,taxes,organiza
5、tioncots,administrativesupport,profits,split-phaseoperations,inspectionanddetection,acceptance,reworking,extrawork,safeguardmeasuresadoptedinatrociousweather,cleanness,finishedproductsprotection,insurance,expensesreceivablebythegovernmentandotherexpensesrelated.FIDIC
6、翻译8.3ProgrammeTheContractorshallsubmitadetailedtimeprogrammetotheEngineerwithin28daysafterreceivingthenoticeunderSub-Clause8.1[CommencementofWorks].TheContractorshallalsosubmitarevisedprogrammewheneverthepreviousprogrammeisinconsistentwithactualprogressorwiththeContr
7、actor’sobligations.Eachprogrammeshallinclude:(a)theorderinwhichtheContractorintendstocarryouttheWorks,includingtheanticipatedtimingofeachstageofdesign,Contractor’sDocuments,procurement,manufacture,inspection,deliverytoSite,construction,erection,testing,commissioninga
8、ndtrialoperation,根据第8.1款【工程开工】的规定,承包商在接到通知后的28天内应向监理提供详细的进度计划。当原计划与实际进度或承包商的责任不符时,承包商也应提交修改的进度计划。每份计划应包括:(a)承包商计划实施工程的秩序,包括设计,承包商文件