1、桥梁建设2017年第47卷第2期(总第243期)112BridgeConstruction,Vol.47,No.2,2017(TotallyNo.243)文章编号:1003-4722(2017)02-0112-05公安长江公铁两用特大桥非通航孔钢桁梁架设技术季强(中铁大桥局集团第四工程有限公司,江苏南京210031)摘要:公安长江公铁两用特大桥非通航孔(6~10号墩)采用4×94.5m连续钢桁梁结构,连续钢桁梁采用双片主桁结构,主桁中心距14.0m、桁高13.0m、节间距13.5m,共28个节间,主桁弦
2、杆采用焊接整体节点,上、下弦杆在节点外采用高强度螺栓拼接。通过对钢桁梁架设方法研究,并结合工程特点及现场情况,该桥非通航孔钢桁梁采用WD70型全回转架梁吊机散拼法安装,在10号墩后方(公安侧)设置架梁拼装支架,自10号墩向6号墩方向逐节间、逐孔架设钢桁梁。其中,9号至10号墩间钢桁梁采用膺架法拼装;8号至9号墩间钢桁梁采用半悬臂拼装架设法拼装;6~8号墩间钢桁梁采用全悬臂拼装法拼装。该桥钢桁梁于2015年9月1日完成,架设过程质量安全可控,架设后钢桁梁线形良好,满足设计要求。关键词:公路铁路两用桥;钢桁
3、梁;整体节点;膺架法;悬臂拼装法;临时支架;桥梁施工中图分类号:U445.466;U448.121文献标志码:AErectionTechniquesforContinuousSteelTrussGirderofNon‐NavigableSpansofGong′anChangjiangRiverRail‐cum‐RoadBridgeJIQiang(The4thEngineeringCo.,Ltd.,ChinaRailwayMajorBridgeEngineeringGroup,Nanjing210031,
4、China)Abstract:Thenon‐navigablespans(PiersNo.6~No.10)ofGong′anChangjiangRiverRail‐cum‐RoadBridgearethecontinuoussteeltrussgirderstructurewithspanarrangement4×94.5m.Thesteeltrussgirderofthebridgeismadeupofthedoublemaintrusses.Thec/cdistanceofthemaintrusse
5、sis14.0m,theheightis13.0m,thepanellengthis13.5mandthemaintrussesaretotallydividedinto28panels.Thepanelpointsforthechordsofthemaintrussesaretheweldedintegralpanelpointsandtheupperandlowerchordsarerespectivelysplicedbythehigh‐strengthboltsoutsidethepoints.
6、Intheerectionofthetrussgirder,throughthestudyoftheerectionmethodsandinconsiderationoftheconstructioncharacteristicsandconstructionconditionsatthesite,itwasdeterminedthatthetrussgirderwastobeassembledpiecebypiece,usingtheWD70fullslewingdeckcranes.Atthebac
7、kofthePierNo.10(Gong′anSide),theassemblingscaffold‐ingswerearranged,thetrussgirderwaserectedpanelbypanelandspanbyspanfromthePiersNo.10toNo.6,ofwhichthetrussgirderoverthePiersNo.9andNo.10waserected,usingthescaffoldingassemblingmethod,thetrussgirderoverthe
8、PiersNo.8andNo.9waserected,usingthesemi‐cantileverassemblingmethodandthetrussgirderoverthePiersNo.6~No.8waserec‐ted,usingthefullcantileverassemblingmethod.TheerectionofthetrussgirderofthebridgewascompletedonSeptember1,2015