1、B13××××××工程监理实施细则(交通标志工程)内容提要:专业工程特点监理工作流程监理工作控制目标及控制要点监理工作方法及措施项目监理机构(章):专业监理工程师:总监理工程师:日期:江苏省建设厅监制目录第一章总则··············································································································2第二章交通标志工程监理······················
2、······································································2一、一般规定·····································································································2二、进场材料检查································································
3、·······························3三、开工报告·····································································································3四、施工监理·····································································································3五、备
4、注············································································································7六、相关监理程序说明··························································································7交通标志工程监理细则第一章总则目的:为了加强高速公路建设项目的交通工程质量管理,
5、合理控制工期和工程费用,使施工监理工作法制化、标准化、规范化、程序化,特制定本细则。依据:依据交通部颁发“公路工程施工监理规范”及相关高速公路蒙蚌段工程合同文件制定。施工监理原则:监理单位和监理人员应按照“严格监理、热情服务、秉公办事、一丝不苟”的原则认真贯彻有关监理的各项方针、政策、法规。认真做好施工监理工作。适用范围:高速公路××段交通工程建设项目备注:本项监理办法有关条款如与业主合同条款有异,以业主合同条款为准。第二章交通标志工程监理一、一般规定以二公里划分为分部工程,分项工程中又分为放线定
6、位、基坑开挖、基础混凝土浇注、支柱安装、交通标志安装等工序。每道工序施工完毕,经自检合格后,再报监理人员检验,上道工序未经监理人员检验认可,不许进入下道工序的施工。本工程适用标准:GB1720漆膜附着力测定法GB2423.17盐雾试验方法GB2893安全色GB3190铝及铝合金加工产品的化学成份GB3194铝及铝合金板材的尺寸及允许偏差GB3199铝及铝合金加工产品的包装、标志、运输、贮存GB3681塑料自然气候暴露试验方法GB3880铝及铝合金轧制板材GB3978标准照明体及照明观测条件GB39
7、79物体色的测量方法GB5237铝合金建筑型材GB5768道路交通标志和标线GB8416视觉信号表面色GB9344塑料氙灯光源暴露试验方法以及涉及上述内容的更新标准。二、进场材料检查1.提供和使用的材料,必须符合图纸要求和有关规定。2.除非图纸规定或监理工程师有指示,否则底座混凝土标号应不低于25号。支柱或其部件应为热镀锌钢材;立柱、横梁、法兰盘的镀锌量不低于GB5768--1999规定的600g/m2要求,紧固件不低于350g/m2。承包人在订货前应将样品及测试资料提交监理工程师批准。3.材料进
8、场后,由监理、安装单位共同交验,现场主要依据合同文件和相关技术规范对到场材料进行外观质量、结构尺寸、防腐层质量、材质证明文件、出厂标志和数量检查。检验时填写《进场材料检验单》。4.原材料进场后,监理人员应对进场的各种原材料进行检查:(1)检查水泥标号、出厂日期及合格证等,工程施工中不得使用过期的水泥。(2)工程用砂和石料应符合图纸和技术规范的规定。三、开工报告分部工程开工报告应说明工程名称、位置桩号、开工条件、施工人员和机械配备情况、施工方案、工艺流程图、质保体系并明确相关负责人、