《隧道二次衬砌断面检查》由会员上传分享,免费在线阅读,更多相关内容在工程资料-天天文库。
1、中铁一局集团秦岭II号隧道结构物检查表日期:日期:测量:复核:秦岭II号隧道I标隧道二次衬砌断面检查里程桩号宽度(m)高度(m)设计实测差值设计实测差值上行线SK65+60011.011.06+0.061417.4721417.503+0.031SK65+61511.01L09+0.091417.8301417.855+0.035SK65+63011.011.07+0.071418.1861418.219+0.033下行线XK65+64011.011.08+0.081416.9621416.998+0.036XK65+65011.011.06+0.0
2、61417.2001417.230+0.030XK65+66011.01L10+0.101417.4361417.468+0.032日期:日期:测量:复核:秦岭II号隧道I标隧道开挖断面检查里程桩号拱顶标高(m)中线平面位置(m)设计实测差值设计实测差值(m)XYXY△XAY上行线SK66+2201432.0651432.133+0.06838687.73244366.22338687.73544366.224+0.003+0.001SK66+2321432.3291432.390+0.06138676.13044363.15938676.12944
3、363.161-0.001+0.002SK66+2481432.6811432.704+0.02338660.66044359.07338660.66244359.070+0.002-0.003下行线XK66+2811432.0131432.084+0.07138650.52344395.53738650.52544395.541+0.002+0.004XK66+2941432.2991432.325+0.02638637.95044392.30538637.94844392.308-0.002+0.003XK66+3001432.6011432.6
4、80+0.07938632.13744390.81938632.13644390.818-0.001-0.001秦岭II号隧道I标隧道初衬断面检查里程桩号拱顶标高(m)中线平面付詈(m)设计实测差值设计实测差值(m)XYXY△XAY上行线SK66+2371432.1391432.174+0.03538671.29644361.88238671.29444361.881-0.002-0.001SK66+2421432.2491432.277+0.02838666.46144360.60538666.45844360.607-0.003+0.002SK6
5、6+2501432.4251432.449+0.02438658.72744358.56238658.72944358.562+0.0020.000下行线XK66+2701431.4711431.498+0.02738661.14744398.31338661.14844398.315+0.001+0.002XK66+2851431.8011431.844+0.04338646.65844384.53838646.65644384.537-0.002-0.001XK66+3021432.3251432.355+0.03038630.19944390.
6、32338630.20144390.320+0.002-0.003I标段桥梁桩基中心位置检查表墩号编亏设计实测差值(m)XYXY△XAY1#墩1#39499.23444715.57239499.22844715.575-0.006+0.0032#39502.14644710.90639502.14944710.911+0.003+0.0053#39505.05844706.24039505.06244706.238+0.004-0.0022#墩1#39482.26744704.98439482.26644704.989-0.001+0.0052#39
7、485.17844700.31839485.17444700.321-0.004+0.0033#39488.09044695.65239488.08844695.653-0.002+0.001