《江苏某食品车间静压桩施工组织设计.doc.doc》由会员上传分享,免费在线阅读,更多相关内容在教育资源-天天文库。
1、江苏大自然食品有限公司17#主车间静压桩施工组织设计编制:校对:审核:江苏地基工程有限公司二00九年八月十日目录一、总体概述·················································································二、施工现场平面布置图··································································三、施工进度计划表和进度保证措施································
2、···················四、各分部分项施工方案及质量保证措施···········································(一)施工方案·············································································1、施工准备工作·································································2、施工工艺及施工步骤方法··················
3、···································3、施工注意事项···································································(二)质量保证措施···································································1、质量管理目标···································································2、技术保证措
4、施···································································3、材料保证措施·······························································五、安全文明施工、环境保护和消防措施·············································1、安全生产目标··························································
5、·····2、安全生产保证体系··························································3、安全施工措施································································4、方明施工、环境保护措施···················································5、消防措施·····················································
6、·················六、项目管理班子人员配备情况·························································七、劳动力、施工机械设备及材料的投入计划和进退场计划···················八、关键施工技术、工艺及工程项目实施的重点、难点和解决方案·······九、雨季、夜晚施工措施····································································十、保证工期措施············
7、······························································十一、新技术、新产品、新工艺、新材料的应用······························十二、地下管线及其他设施的加固、保护等特殊措施·····························一、总体概述㈠、工程概况:拟建江苏大自然食品有限公司17#主车间位于涟水开发区。该工程由江苏城建校建筑规划设计院设计。设计采用预应力管桩处理地基,工程桩选用江苏省标准图集《先张法预应力混凝土管桩》苏G03-
8、2002,桩型为PHC—400(90)A—C80-23M。桩端持力层为10层粘土层,桩尖进入持力层不少于1米。㈡、总体施工部署2.1、总体施工进度划分⑴施工准备施工机械进场并调试、施工用电的设置、临时设施的搭建、预制管桩进场、定位放线⑵工程施工桩位