1、荣盛房地产发展股份有限公司项目开发业务规范(第一版)二〇〇八年七月七日第58页共59页提纲一、市场拓展1、土地信息获取·································································(第四条,N天)2、投资意向前期市场调研·····················································(第五条,15天)3、意向土地持续跟踪···························································(第六条,37天)4、土地公告及竞买·

2、·····························································(第七条,21天)二、市场营销1、项目可研前期市场调研·····················································(第八条,15天)2、土地购置前期深度市场调研················································(第九条,15天)3、项目启动前期市场深度研究················································(第十条,30天)4、

3、项目亮相前准备·························································(第十一条,202天)5、项目亮相··································································(第十二条,60天)6、项目公开期································································(第十三条,30天)7、项目开盘销售················································

4、··············(第十四条,15天)8、项目日常销售·······························································(第十五条,N天)9、项目清盘···································································(第十六条,90天)三、银行融资1、贷款意向合作单位调研·················································(第十第58页共59页七条,45天)2、贷款方案公司内部审批··········

5、········································(第十八条,37天)3、贷款资料组卷并上报支行··············································(第十九条,65天)4、贷款资料完成分行审批并上报省行···································(第二十条,41天)5、完成省行(总行)审批、取得贷款批文····························(第二十一条,39天)6、银行贷款的放款·············································(

6、第二十二~二十三条,30天)7、土地抵押转在建工程抵押·············································(第二十四条,45天)8、确定按揭贷款合作单位················································(第二十五条,15天)四、工程建设1、规划设计任务书编制及审批······························(第二十六~二十七条,10天)2、规划方案设计及内部审批·································(第二十八~三十二条,87天)3、项目规划方案政府报批··

7、··································(第三十三~三十六条,96天)4、单体工程设计··················································(第三十七~四十条,56天)5、单体工程预算与招投标···································(第四十一~四十四条,142天)6、单体工程施工············································

当前文档最多预览五页,下载文档查看全文

此文档下载收益归作者所有

当前文档最多预览五页,下载文档查看全文
温馨提示:
1. 部分包含数学公式或PPT动画的文件,查看预览时可能会显示错乱或异常,文件下载后无此问题,请放心下载。
2. 本文档由用户上传,版权归属用户,天天文库负责整理代发布。如果您对本文档版权有争议请及时联系客服。
3. 下载前请仔细阅读文档内容,确认文档内容符合您的需求后进行下载,若出现内容与标题不符可向本站投诉处理。
4. 下载文档时可能由于网络波动等原因无法下载或下载错误,付费完成后未能成功下载的用户请联系客服处理。