1、StandardFAC-013-2—AssessmentofTransferCapabilityfortheNear-termTransmissionPlanningHorizonA.Introduction1.Title:AssessmentofTransferCapabilityfortheNear-TermTransmissionPlanningHorizon2.Number:FAC-013-23.Purpose:ToensurethatPlanningCoordinatorshaveamethodologyfor,
2、andperformanannualassessmenttoidentifypotentialfutureTransmissionSystemweaknessesandlimitingFacilitiesthatcouldimpacttheBulkElectricSystem’s(BES)abilitytoreliablytransferenergyintheNear-TermTransmissionPlanningHorizon.4.Applicability:4.1.PlanningCoordinators5.Effe
3、ctiveDate:Inthosejurisdictionswhereregulatoryapprovalisrequired,thelatterofeitherthefirstdayofthefirstcalendarquartertwelvemonthsafterapplicableregulatoryapprovalorthefirstdayofthefirstcalendarquartersixmonthsafterMOD-001-1,MOD-028-1,MOD-029-1,andMOD-030-2areeffec
4、tive.Inthosejurisdictionswherenoregulatoryapprovalisrequired,thelatterofeitherthefirstdayofthefirstcalendarquartertwelvemonthsafterBoardofTrusteesadoptionorthefirstdayofthefirstcalendarquartersixmonthsafterMOD-001-1,MOD-028-1,MOD-029-1andMOD-030-2areeffective.B.Re
5、quirementsR1.EachPlanningCoordinatorshallhaveadocumentedmethodologyitusestoperformanannualassessmentofTransferCapabilityintheNear-TermTransmissionPlanningHorizon(TransferCapabilitymethodology).TheTransferCapabilitymethodologyshallinclude,ataminimum,thefollowinginf
6、ormation:[ViolationRiskFactor:Medium][TimeHorizon:Long-termPlanning]1.1.Criteriafortheselectionofthetransferstobeassessed.1.2.AstatementthattheassessmentshallrespectknownSystemOperatingLimits(SOLs).1.3.Astatementthattheassumptionsandcriteriausedtoperformtheassessm
7、entareconsistentwiththePlanningCoordinator’splanningpractices.1.4.Adescriptionofhoweachofthefollowingassumptionsandcriteriausedinperformingtheassessmentareaddressed:1.4.1.Generationdispatch,includingbutnotlimitedtolongtermplannedoutages,additionsandretirements.1.4
8、.2.Transmissionsystemtopology,includingbutnotlimitedtolongtermplannedTransmissionoutages,additions,andretirements.1.4.3.Systemdemand.1.4.4.Currentapprov