外墙岩棉板保温施工方案

外墙岩棉板保温施工方案

ID:22791173

大小:978.08 KB

页数:27页

时间:2018-10-31

外墙岩棉板保温施工方案_第1页
外墙岩棉板保温施工方案_第2页
外墙岩棉板保温施工方案_第3页
外墙岩棉板保温施工方案_第4页
外墙岩棉板保温施工方案_第5页
资源描述:

《外墙岩棉板保温施工方案》由会员上传分享,免费在线阅读,更多相关内容在行业资料-天天文库

1、外墙保温专项施工方案外墙外保温施工技术方案27外墙保温专项施工方案目录第一章编制依据·······································6第二章工程概况·······································6第三章施工部署·······································7第一节施工组织管理机构·······································7第二节施工管理构架图····················

2、·····················7第三节施工部署···············································8第四章施工管理措施···································9第一节工期保证措施···········································9第二节质量保证措施27外墙保温专项施工方案··········································10第三节安全保证措施········

3、··································10第四节文明施工保证措施······································11第五章施工工艺······································12第一节施工条件··············································12第二节施工工具··············································12第三节系统构造和材料性能·

4、···································12第四节施工工艺流程··········································16第五节保温施工··············································17第六章施工验收·····································21第七章成品保护·····································24第八章各类安全事故的抢险措施······

5、·················2427外墙保温专项施工方案第一节触电事故的抢险措施···································24第二节高空坠落触电事故的抢险措施··························25第三节机械伤害事故的抢险措施······························26第四节火灾事故的抢险措施··································26第五节消防措施································

6、············27第十章冬季和雨季施工措施··························27第一章编制依据(1)本工程外墙外保温设计说明及设计变更文件(2)《建设节能工程施工质量验收规范》GB50411—2007(3)《建筑工程施工质量验收统一标准》GB50300—2013(4)《公共建筑节能设计标准》GB50189—2015(5)《夏冬热冷地区居住建筑节能设计标准》JGJ134-2010(6)《安徽省公共建筑节能设计标准》DB34/1467-2011(7)《安徽省居住建筑节能设计标准》DB3

7、4/1466-2011(8)《岩棉板外墙外保温系统应用技术导则》DBHJ/T002-2011(9)《岩棉板外墙外保温系统应用技术规程》DB34/T1859-2013(10)《建筑幕墙》GB/T21086-2007第二章工程概况1、工程名称:2、建设单位:3、设计单位:27外墙保温专项施工方案4、监理单位:5、施工单位:6、保温类型:本项目采用涂料饰面岩棉板保温系统且岩棉板密度≥160Kg/m³,外墙保温厚度30mm。7、工期目标:总工期以合同要求(具体以施工进度计划为准)8、质量目标:合格第三章施工部署第一节

8、施工组织管理机构一、项目经理负责制成立以项目经理为首的工地办公室,集中办公,按工作职责进行分工管理,由项目经理统一指挥。项目经理以下配备项目技术负责人、材料员、安全员、质检员、施工员。二、管理人员职责(1)项目经理:代表企业法人,全面负责工程的统筹、安排和决策。(2)项目技术负责人:协助项目经理协调各部门与施工班组的关系;协调与总包、监理、主管部门及其他有关职能部门的关系,及时解决遇到的各种问题,负

当前文档最多预览五页,下载文档查看全文

此文档下载收益归作者所有

当前文档最多预览五页,下载文档查看全文
温馨提示:
1. 部分包含数学公式或PPT动画的文件,查看预览时可能会显示错乱或异常,文件下载后无此问题,请放心下载。
2. 本文档由用户上传,版权归属用户,天天文库负责整理代发布。如果您对本文档版权有争议请及时联系客服。
3. 下载前请仔细阅读文档内容,确认文档内容符合您的需求后进行下载,若出现内容与标题不符可向本站投诉处理。
4. 下载文档时可能由于网络波动等原因无法下载或下载错误,付费完成后未能成功下载的用户请联系客服处理。