1、此文档收集于网络,如有侵权,请联系网站删除目录1工程概况······································································································22施工准备······························································································23施工工艺······················
2、································································24施工资源计划····························································································45施工要求及措施····················································································4
3、6成品保护措施················································································67安全文明施工·····························································································6此文档仅供学习与交流此文档收集于网络,如有侵权,请联系网站删除1工程概况本工程为中房青岛嘉苑一期工程,工程位于莱州市沙河镇,由青岛中房集团
4、莱州中房有限公司开发建设,青岛东盛建筑设计事务所设计,莱州市全盛建设项目管理有限公司监理,青岛一建集团有限公司总承包施工。工程包括2栋网点房,16栋住宅楼,建筑总面积为62496m2,其中住宅建筑面积54573m2,商业、物业、设备用房等建筑面积7923m2结构形式为框架结构,基础形式采用独立基础,住宅层数为1+6、1+5层,6层(其中1+5、1+6住宅地上一层为车库、储藏室),顶层均为阁楼,建筑层高2.8m,网点为2层,局部3层,建筑层高3.9m。2施工准备2.1施工准备2.1作业条件此文档仅供学习与交流此文
5、档收集于网络,如有侵权,请联系网站删除1、填充墙已砌筑完毕。2、主体结构已完成,脚手架眼已封堵完。对主体结构工程进行核查验收,并取得结构验收手续后,方可进行抹灰工程。3、基层墙面已清洗干净,无浮土、油渍、空鼓及松动等。2.2材料准备1、水泥采用32.5R普通硅酸盐水泥。进场必须有产品质量证明书,并按有关规定要求取样,送指定检测单位检测,经检验合格后方可使用。2、砂为中砂,使用前过5mm孔径的筛,含泥量不超过3%。3施工工艺3.1施工程序3.1.1厨房间、卫生间:基层处理→铺设300mm钢丝网→洒水湿润→甩浆→找
6、方→贴灰饼、冲标筋→1∶3水泥砂浆压光后拉毛。3.1.2其它房间:(采用局部抹灰,即:加气砼墙面抹灰。)基层处理→铺设300mm钢丝网→洒水湿润→甩浆→找方→贴灰饼、冲标筋→1∶0.3∶2.5混合砂浆压光(外墙1∶3水泥砂浆压光后拉毛)3.2施工工艺1、基层处理:抹灰前检查加气砼墙面,对松动、灰浆不饱满的拼缝及梁、板下的顶头缝用干硬性砂浆填塞密实。对于砼墙面凸出部分及杂物应先剔凿平整,然后用刷子蘸水把表面残渣和浮尘清理干净2、钉钢丝网:基层处理完后,在砌体与框架柱、梁、构造柱等交接处钉钢丝网。用钢钉或射钉每20
7、0-300㎜加铁片固定,钢丝网的宽度不应小于220㎜,与不同基层的搭接宽度每边不少于100㎜,挂网要做到均匀、牢固,在砌体上不得用射钉固定。此文档仅供学习与交流此文档收集于网络,如有侵权,请联系网站删除3、洒水湿润:用水将墙体湿润,喷水要均匀,不得遗漏,墙体表面吸水深度控制在20㎜左右。4、甩浆:用界面剂:水泥:过筛细砂=1:1:1.5的水泥砂浆做甩浆液,要使墙壁面布点均匀,不应有漏涂。浇水养护24小时,待水泥砂浆达到一定强度后再抹灰。5、找方:先以跨度较大的两面墙体所在的轴线各找出一条控制线,然后以这两条控制
8、线确定两条较短的控制线,相邻控制线间要互相垂直。6、贴饼、冲筋:在每一面墙上抹20㎜灰饼,然后拉通线做冲筋,冲筋的宽度和厚度与灰饼相同,冲筋时,以垂直方向的上下两个灰饼之间的厚度为准,用灰饼相同的砂浆冲筋,抹好冲筋砂浆后,用硬尺与冲筋通,一次通不平,可补灰,直至通平为止,冲筋面宽50mm,底宽约80mm,墙面不大时,可只做两条冲筋。冲筋后应检查冲筋的垂直平整度,误差在0.5mm以上者,