1、广深港客运专线福田车站及相关工程益田路隧道斜井监理实施细则编制:审核:审批:铁四院监理联合体广深港客专工程*****************二〇〇九年四月目录1、监理项目概述┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅11.1、工程概况┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅11.2、斜井净空断面┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅11.3、斜井支护形式┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅11.4、斜井围岩情况┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅1

2、2、监理工作范围、目标及内容┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅22.1、监理工作范围┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅32.2、监理工作目标┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅32.3、监理工作内容┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅53、监理工作依据┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅93.1、国家或地方现行的有关工程建设的法律、法规和章程┅┅┅┅┅┅┅┅┅93.2、国家和铁道部现行的有关工程建设的规范、规程和技术标准┅┅┅┅┅┅94、施

3、工准备阶段的监理工作┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅114.1、设计文件的核对┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅114.2、测量点位交接┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅124.3、审查施工单位编写的实施性施工组织设计┅┅┅┅┅┅┅┅┅┅┅┅┅124.4、控制测量┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅134.5、施工场地与临时工程施工监理┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅145、超前地质预测预报系统┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅155.1

4、、隧道地质预报的目的┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅155.2、超前地质预测预报的内容┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅155.3、隧道超前地质预报工作程序┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅165.4、超前地质预报的方法┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅175.5、地质调查法┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅185.6、洞内、洞外实时监测┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅185.7、依据地质超前预报及监测资料对可能的涌(突)水突泥地段的施工方案进行设计┅┅┅

5、┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅19第41页共42页6、监控量测监理实施细则┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅196.1、监控测量目的┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅206.2、监理工作方法┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅206.3、隧道监控量测的内容、方法及要求┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅206.4、监控量测管理┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅246.5、资料的收集和管理┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅2

6、66.6、进行分析回归,建立管理等级┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅266.7、围岩稳定性的综合判别┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅266.8、根据位移变化速度判别┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅276.9、根据位移时态曲线的形态来判别┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅276.10、地质素描及观察┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅286.11、发出信息反馈施工及设计┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅287、附属工程监理要点┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅

7、327.1运营通风土建工程监理要点┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅327.2、消防监理要点┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅327.3、电缆槽监理要点┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅327.4、洞内附属构筑物监理要点┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅327.5、其他附属监理要点┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅338、各项准备工作及控制措施监理要点┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅338.1、技术准备┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅33

8、8.2、物资准备┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅338.3、设备准备┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅338.4、控制措施┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅┅33第41页共42页1、监理项目概述1.1、工程概况益田路隧道斜井是为了加快施工进度,减少矿山法隧道施工与盾构法隧道施工的干扰,

当前文档最多预览五页,下载文档查看全文

此文档下载收益归作者所有

当前文档最多预览五页,下载文档查看全文
温馨提示:
1. 部分包含数学公式或PPT动画的文件,查看预览时可能会显示错乱或异常,文件下载后无此问题,请放心下载。
2. 本文档由用户上传,版权归属用户,天天文库负责整理代发布。如果您对本文档版权有争议请及时联系客服。
3. 下载前请仔细阅读文档内容,确认文档内容符合您的需求后进行下载,若出现内容与标题不符可向本站投诉处理。
4. 下载文档时可能由于网络波动等原因无法下载或下载错误,付费完成后未能成功下载的用户请联系客服处理。