《石化监理表格大全》由会员上传分享,免费在线阅读,更多相关内容在行业资料-天天文库。
1、1SH/T3903-A.1工程开工/复工报审表WorksCommencement/ResumptionApprovalRequest工程名称WorksTitle:编号ItemNo:致(监理单位)To(CS/CMC)我单位承担的工程,已完成了以下各项工作,具备了开工/复工条件,特此申请施工,请核查并签发开工/复工指令。Wehavefulfilledthefollowingactivitiesfortheworkcontractedbyus,theworkscommencement/worksresumptionconditionsareavailable,ther
2、eforetheconstructionisappliedhereby,pleasereviewandissueworkscommencement/worksresumptionorders.附Attached:1开工报告commencementReport;2证明文件Supportingdocuments。承包单位(章)Contractor(Chop)项目经理ProjectManage日期Date审查意见ReviewComments:项目监理机构CS/CMC总监理工程师ChiefSupervisionEngineer日期DateSH/T3903-A.2施工组织
3、设计(方案)报审表ConstructionOrganizationDesignApprovalRequest工程名称WorksTitle:编号ItemNo:致(监理单位)To(CS/CMC)我方已根据施工承包合同的有关规定完成了工程施工组织设计(方案)的编制,并经我单位技术负责人审查批准,请予以审查。Accordingtotherelatedregulationsoftheconstructioncontract,wehavecompletedthepreparationoftheconstructionorganizationdesign,andithasbe
4、enreviewedandapprovedbythetechnicalresponsiblepeopleofourcompany,pleasereviewit.附Attached:施工组织设计/施工方案。ConstructionOrganizationDesign/ConstructionPlan。承包单位(章)Contractor(Chop)项目经理ProjectManager日期Date专业监理工程师审查意见Reviewcommentsfromdisciplinesupervisionengineer:专业监理工程师DisciplineSupervision
5、Engineer日期Date总监理工程师审核意见Reviewcommentsfromchiefsupervisionengineer:项目监理机构CS/CMC总监理工程师ChiefSupervisionEngineer日期DateSH/T3903-A.3分包单位资格报审表SubcontractorQualificationApprovalRequest工程名称WorksTitle:编号ItemNo:致(监理单位)To(CS/CMC)经考察,我方认为拟选择的(分包单位)具有承担下列工程的施工资质和施工能力,可以保证本工程项目按合同的规定进行施工。分包后,我方仍承担
6、承包合同的全部责任。请予以审查和批准。Afterinvestigation,wethinktheproposed(subcontractor)hasthequalificationandcapabilityforcontractingthefollowingworks,andcanassurethatthisworkswillbeconstructedasperthecontractregulations.Aftersubcontractingthisworks,westillholdthewholeresponsibilitiesofthelumpsumcon
7、tractor.Pleasereviewandapproveit.附Attached:1分包单位资质材料SubcontractorQualificationDocuments;2分包单位业绩材料SubcontractorPerformanceDocuments。分包工程名称(部位)Subcontractedworks(Location)工程数量WorksQuantity拟分包工程合同额Contractpriceofproposedsubcontractedworks分包工程占全部工程Percentageofsubcontractedworks合计Totals承包
8、单位(章)Contrac