《泉州晋江大桥斜拉桥主梁施工》由会员上传分享,免费在线阅读,更多相关内容在行业资料-天天文库。
1、泉州晋江大桥斜拉桥主梁施工杨奉举81文章编号:1003—4722(2010)05—0081-04泉州晋江大桥斜拉桥主梁施工杨奉举(中铁大桥勘测设计院有限公司,湖北武汉430050)摘要:泉州晋江大桥主桥为(200+165)m独塔双索面预应力混凝土斜拉桥,主梁横断面为双波浪形箱梁。该桥主梁采用普通挂篮对称悬臂施工,挂篮底平台刚度大,外模采用整体钢模,内模采用拆装式模板;0号节段采用水中支架分段施工,并设置后浇段;梁上张拉斜拉索。为加快施工进度,增加了主跨支架现浇长度,使主跨与边跨同步对称合龙。同时,在桥塔中横梁施工完后,设置安全
2、隔离装置,实现塔、梁交叉施工。在悬臂施工过程中,主梁横梁底部施加临时体外预应力,2号节段施工时设置临时反拉梁。主梁合龙时,在合龙口每个箱内设置三榀体外桁架式劲性骨架,并加强合龙口处的支架以抵抗合龙后主梁的反力。关键词:斜拉桥;预应力混凝土结构;箱形梁;施工方法;桥梁施工中图分类号:U448.27;U445.4文献标志码:AConstructionofMainGirderofCable-StayedBridgeofQuanzhouJinjiangRiverBridgeYANGFeng-jU(ChinaRailwayMajorBr
3、idgeReconnaissance&DesignInstituteCo.,Ltd.,Wuhan430050,China)Abstract:ThemainbridgeofQuanzhouJinjiangRiverBridgeisaprestressedconcretecable—stayedbridgewithasinglepylonanddoublecableplanesandwithspanarrangement(2OO+165)m.ThecrosssectionofthemaingirderoftheBridgeisde
4、signedasadual—waveshapeboxgirderandthegirderisconstructedbythecommonformtravelerbythebalancedcantilevermethod.Therigidityofthebottomplatformofthetravelerisgreat,theexternalformworkthereofistheintegralsteeIonewhiletheinternalformworkiSthedetachableone.ThesegmentNo.0i
5、scastinsectionsOnscaffoldingstandinginwaterandthesuccessivesegmentstobecastareprepared.Thestaycablesaretensionedatthegirder.Tospeeduptheconstruction,thelengthofcast—in—situonscaffoldingforthemainspanisincreasedinordertoensurethatthemainspanandsidespancanbeclosedinsa
6、mestepandinasymmetricway.Moreover,aftertheconstructionofthemiddlecrossbeamofthepyloniscompleted,thesafetyisolatingdevicesareinstalledandthustheparal—lelconstructionofthepylonandgirdercanberealized.Intheprocessofthecantileverconstruc—tion,thetemporaryexternalprestres
7、singisappliedtothebottomofthecrossbeamsofthemaingirderandatthetimethesegmentNo.2isconstructed,thetemporarycounterpullbeamsarear-ranged.Beforethemaingirderisclosed,threeexternalstiffeningskeletonsoftrusstypearesetineachboxattheclosuregapandthescaffoldingattheclosureg
8、apisreinforcedtoresistthere—actionforcefromtheclosedgirder.Keywords:cable—stayedbridge;prestressedconcretestructure;boxgirder;construction