《预制钢筋混凝土装配式结构的施工组织方案》由会员上传分享,免费在线阅读,更多相关内容在行业资料-天天文库。
1、WORD整理版单层工业厂房预制钢筋混凝土装配式结构安装施工方案班级:11造价五班姓名:刘媛学号:55号范文范例参考指导WORD整理版目录工程概况····················································第1页总括施工工艺················································第1页第一章:单层工业厂房结构安装方案····························第2页1.场地清理与铺设············································第2页2.基础准备····
2、··············································第2页3.构件的运输、堆放、拼装和加固······························第3页4.构件的检查、清理··········································第4页5.构件的弹性、编号··········································第5页第二章:构件吊升方法、技术··································第5页1.柱的吊装范文范例参考指导WORD整理版··················
3、································第5页1.吊车梁的吊装··············································第7页2.屋架的吊装················································第8页3.屋面板的吊装··············································第9页4.天窗架的吊装··············································第10页第一章:起重机械的选择·····················
4、·················第10页第二章:结构吊装方案········································第10页第三章:起重机的开行路线及停靠位置··························第11页第四章:构件的平面布置······································第13页第五章:质量保证措施·········································第13页1.质量保证措施范文范例参考指导WORD整理版············································
5、··第13页1.质量通病及防治措施········································第14页第一章:安全生产及文明施工措施······························第15页第二章:成品保护措施········································第16页范文范例参考指导WORD整理版一、工程概况某单位单层工业厂房工程,2011年5月1日正式开始施工,预计施工期10个月。工程概况如下:主楼:铸造车间,跨度21M,柱距6M,主体结构:预制钢筋混凝土装配式排架结构,巨星牛腿柱6t,柱埋入混凝土杯形基础0.6M。其它:T型
6、预应力吊车梁,重1.4t预应力18t折行屋架,重6t。现浇混凝土上人平屋面,坡度2%,Ⅱ级防水,采用混凝土结构自防水与SBS高聚物改性沥青防水卷材3mm+3mm设防,100厚聚苯板保温材料,陶粒混凝土最薄处30mm找坡。二次结构:加气混凝土小型砌块装饰:简单装修(水泥砂浆底面、耐水腻子四白落地)水利水电出版社二、总括施工工艺本方案包括:地下工程,预制工程,结构安装工程,维护及装饰。施工顺序:(一)基础工程施工顺序:基础工程施工的施工顺序为:基坑挖土——钎探验槽———做垫层——绑扎钢筋——安装模板——浇筑混凝土——养护——回填土等。在确定施工顺序是,厂房柱基础与设备基础的施工顺序它影响到主
7、体结构和设备安装的方法与时间。(二)预制工程的施工顺序,单层工业构件的预制。工厂预制与工地预制相结合的方法进行,一般重大,较大或运输不便的可现场预制。本工程选择先张法预应力混凝土工程。顺序为:支座准备——刷隔离剂——铺放预应力钢筋——张拉——按侧模支横向筋——浇筑混凝土——养护——放张拉预应力筋——脱模——出槽——堆放预制构件的混凝土轴心抗拉强度应达到设计值的75%以上才可以起吊。(三)结构安装的施工的顺序:安装柱子、连系梁、吊车梁