《苏州绿地中央广场三号地块项目夏季施工方案》由会员上传分享,免费在线阅读,更多相关内容在教育资源-天天文库。
1、苏州绿地中央广场项目地块三夏季施工方案目录一.编制依据···············································2二.工程概况··············································2三.工程夏季施工任务······································2四.夏季施工准备··········································2五.夏季施工主要技术措施····························
2、······3(一).混凝土工程······································3(二).模板工程········································4(三).钢筋工程········································5(四).防水工程········································5(五).砌筑工程········································5(六).雨期施工焊接管理·····
3、···························5(七).塔吊············································5浙江港海建设集团有限公司15苏州绿地中央广场项目地块三夏季施工方案(八).脚手架工程······································6六.混凝土夏季施工的质量通病及预防措施····················6七.夏季施工安全专项措施··································7(一).防暑降温措施···········
4、·························7(二).雨季施工安全措施································7(三).安全防护措施····································8(四).防台风、防暴雨工作措施··························9八.夏季施工应急预案措施··································10(一).预防高处坠落的预防措施·························10(二).火灾、爆炸事故预防措施···
5、······················10(三).抗台风预防措施·································11(四).防中暑应急预案措施·····························13九.应急救援路线·········································13浙江港海建设集团有限公司15苏州绿地中央广场项目地块三夏季施工方案一、编制依据1、《建筑工程质量检查与验收手册》2、《施工组织设计》3、《本项目施工总平面图》二、工程概况工程概况序号项目内容1工程名称苏州绿
6、地中央广场三号地块项目2工程地址苏州市科技城龙山路与科发路交叉口3建设单位绿地集团苏州高新置业有限公司4设计单位上海正轶建筑设计有限公司5勘察单位江苏省地质工程有限公司6建筑功能地下室为库房、停车场,商铺,地面楼层为商业用房7建筑面积及规模总建筑面积:约66406.47㎡,层数及单体建筑面积:3#楼为地下二层,地面36层.8檐高建筑檐高度:150m。9墙体类型框架柱、核心筒,内墙砂加气砼砌块10屋面防水卷材、XPS挤塑聚苯板、钢筋混凝土平屋面11幕墙玻璃幕墙12防水SBS改性沥青防水卷材、防水涂膜13楼地面水泥楼地面14内墙混合砂
7、浆抹面15外墙玻璃幕墙。16保温XPS挤塑聚苯板、50厚岩棉带17标高:3#楼为4.2m,室内外高差0.2m结构概况序号项目内容1结构类型框架—核心筒2基础类型桩筏基础浙江港海建设集团有限公司15苏州绿地中央广场项目地块三夏季施工方案3抗震设防烈度6度4建筑结构安全等级二级5耐火等级一级6钢筋级别HPB300、HRB335、HRB400E三、工程夏季施工任务按工程进度计划安排,夏季主要从事主体结构施工。四、夏季施工准备(一)技术准备1、施工技术方案(措施)的制定必须以确保施工质量及生产安全为前提,具有一定的技术可靠性和经济合理性。
8、(二)生产准备根据制定的进度计划安排好施工任务及现场准备工作。(三)资源准备根据制定的计划组织好材料、施工仪表、消防器具及职工劳动保护用品等的准备工作。五、夏季施工主要的技术措施(一)混凝土工程夏季气温高、湿度低、干燥快,对于新浇筑混凝土可能出现凝