1、Xxx地块A区安置区附着式升降脚手架专项施工方案xxx集团有限公司72xxxxx区安置区附着式升降脚手架专项施工方案程序签名职称日期编制专业负责人审核项目技术负责人公司技术部门公司质量部门公司安全部门批准公司总工xxx有限公司72目录目录························································1第一章工程概况···········································2一、工程概况·················

2、··························2二、施工布置···········································2三、施工要求···········································2四、技术保证条件·······································4第二章编制依据···········································11第三章施工计划················

3、···························12一、施工进度计划·······································1272一、材料及设备计划·····································13第一章施工工艺技术·······································15一、技术参数···········································15二、安装施工方法·············

4、··························17三、底部、离墙、立面封闭及特殊部位的处理方法···········27四、架体提升施工方法···································29五、架体下降施工方法···································31六、拆除施工方法·······································32七、检查验收······································

5、·····33第二章施工安全保证措施···································3972一、组织保障···········································39二、技术措施···········································39三、应急预案···········································46第一章劳动力及设备计划·····························

6、······53第二章防雷用电措施·······································54第三章设计计算···········································55附件···············································66第一章工程概况一、工程概况xx拆迁安置区)1#、2#、3#、4#楼项目位于xxx。建筑总高为86.40m,其中标准层为28层,标准层层高为2.85m,附着式升降脚手架从标高+9.

7、1572m开始组装,架顶提升至标高+89.50m,待主体施工完成后进行装饰工程附着式升降脚手架又从上往下滑,起到结构施工外防护和外装饰使用等作用。二、施工布置1、该系统为一次性安装,安装搭设完成后自行升、降,不占用塔吊工作时间。附着升降脚手架的架体及机位沿建筑结构外围布置。由于建筑结构外围结构变化,相应附着支撑的长度也随着结构发生变化。考虑到该工程的结构特点、外墙形状和建筑物层高,以及提升架的安装原理,每单元整体布置为A、B两片升降,A片设置18个机位,编号为A1至A18,B片设置16个机位,编

8、号为B1至B16,机位平面布置见附后机位平面布置图。本工程的升、降脚手架从标准层第一层顶开始搭设,逐层提升,架顶升至女儿墙顶高处。外墙装饰施工时再从上,下降至搭设位置后拆除。该工程临边防护、电梯口防护、塔吊防护、水平防护以及内采光井的防护等由项目部自行负责,本方案不做详细说明。三、施工要求1、编制施工方案前必须有完整的设计图纸。2、所有外架用材料符合质量要求。3、脚手架应在设计要求范围内使用。严禁超出使用规定使用。4、在大雨、大雪、浓雾和五级以上大风等视线不良的情况下禁止对脚手架进行搭拆以及升降

当前文档最多预览五页,下载文档查看全文

此文档下载收益归作者所有

当前文档最多预览五页,下载文档查看全文
温馨提示:
1. 部分包含数学公式或PPT动画的文件,查看预览时可能会显示错乱或异常,文件下载后无此问题,请放心下载。
2. 本文档由用户上传,版权归属用户,天天文库负责整理代发布。如果您对本文档版权有争议请及时联系客服。
3. 下载前请仔细阅读文档内容,确认文档内容符合您的需求后进行下载,若出现内容与标题不符可向本站投诉处理。
4. 下载文档时可能由于网络波动等原因无法下载或下载错误,付费完成后未能成功下载的用户请联系客服处理。