1、工程名称松花江哈尔滨城区段松浦堤改线工程及哈尔滨市松花江北岸堤防防汛抢险通道工程二标段施工单位黑龙江龙航工程总承包有限责任公司项目名称部位计算草图及几何尺寸见附表计算式及说明:1、已清基总量为:67412m³,其中包括渗水井土方量488.25m³。上月结算21600m³,本月完成45812m³。2、本月土方碾压填筑完成:55908m³3、混凝土路面拆除计算式1号混凝土路长98m×宽2.8m×0.2m厚=54.88m³2号混凝土路长77.96m×宽4m×0.2m厚=62.37m³3号混凝土路长78.21m×宽4m×0.2m厚=62.57m³4号混凝土路长82.52m×宽4m×0.2

2、m厚=66m³5号混凝土路长123.2m×宽5m×0.2m厚=123.2m³6号混凝土路长16.6m×宽4m×0.2m厚=13.28m³合计:382.3m³上月完成混凝土路面拆除100m³,本月完成拆除为382.3m³-100m³=282.3m³制表人:监理:工程量计算表he"governingforthepeople","Nomattertheinterestsofthemasses"conceptunderstandingisnotinplace.Thespecificworktreatswiththedeployment,afewleadingcadrescomplaint

3、hatworkistoocomplicated,toomuchresponsibility,thepressureistoolarge,toomuchemphasisonthedifficultyofthework.Forexample,noncoalmine清基工程量水利桩号市政桩号断面积平均断面面断面距离体积k0+90021+80016.5      27.1625678.9k0+92521+82537.810 0   48.98251224.38k0+95021+85060.140 0   64.64251615.88k0+97521+87569.130 0   73.28

4、251832.00k1+00021+90077.430 0   85.21252130.25k1+02521+92592.990 0   95.27252381.75k1+05021+95097.550 0   130.34253258.5k1+07521+975163.130 0   168.065254201.625k1+10022+000173     157.095253927.375k1+12522+025141.190 0   139.00253474.88k1+15022+050136.80 0   142.435253560.875k1+17522+075148.

5、070 0   146.53253663.13k1+20022+100144.980 0   141.24253530.88k1+22522+125137.490 0   144.515253612.875k1+25022+150151.540 0   143.545253588.625k1+27522+175135.550 0   153.145253828.625k1+30022+200170.740 0   159.42253985.50k1+32522+225148.10 0   149.455253736.375k1+35022+250150.810 0   135.3

6、85253384.625k1+37522+275119.960 0   126.895253172.375k1+40022+300133.830 0   130.84253270.88k1+42522+325127.840 0   114.55252863.75k1+45022+350101.26   合计    66924he"governingforthepeople","Nomattertheinterestsofthemasses"conceptunderstandingisnotinplace.Thespecificworktreatswiththedeployment

7、,afewleadingcadrescomplainthatworkistoocomplicated,toomuchresponsibility,thepressureistoolarge,toomuchemphasisonthedifficultyofthework.Forexample,noncoalmine117.5m土方碾压工程量水利桩号市政桩号断面积平均断面面断面距离体积k0+90021+8003.2512.34525308.625k0+92521+82521.4400

当前文档最多预览五页,下载文档查看全文

此文档下载收益归作者所有

当前文档最多预览五页,下载文档查看全文
温馨提示:
1. 部分包含数学公式或PPT动画的文件,查看预览时可能会显示错乱或异常,文件下载后无此问题,请放心下载。
2. 本文档由用户上传,版权归属用户,天天文库负责整理代发布。如果您对本文档版权有争议请及时联系客服。
3. 下载前请仔细阅读文档内容,确认文档内容符合您的需求后进行下载,若出现内容与标题不符可向本站投诉处理。
4. 下载文档时可能由于网络波动等原因无法下载或下载错误,付费完成后未能成功下载的用户请联系客服处理。