1、2z101040建设工程项目目标的动态控制(Dynamiccontrolof2z101040constructionprojectobjective)Dynamiccontrolof2Z101040constructionprojectobjective(P28~31)2Z101041dynamiccontrolmethodformasteringprojectobjectives(P28~29)Thedynamiccontrolofprojectobjectivesisthemostbasicmethodologyofprojectmanagement.Workingprocedu
2、reofdynamiccontrolof1.projectobjectives(1)preparation:goaldecomposition;determiningtheplannedvalueoftargetcontrol(2)dynamictrackingandcontrolCollectComparisonRectifyingdeviation(3)adjustprojectobjectivesifnecessary2.projecttargetdynamiccontroldeviationcorrectionmeasuresForexample:changetheconst
3、ructionmachinerybelongstotechnicalmeasures;changethenumberofconstructionmachinerybelongstomanagementmeasures.Whentheprojectgoalsareoutofcontrol,thefirstconsiderationistotakeorganizationalmeasures.Whentheprojectgoalisoutofcontrol,thefirstconsiderationistotaketechnicalmeasuresandignoretheorganiza
4、tionalmeasuresandmanagementmeasuresthatmayorshouldbetaken.Priorcontrolof3.projectobjectivesThecoreofthedynamiccontrolofprojectobjectivesistocomparetheplannedvalueandactualvalueoftheprojectobjectivesperiodicallyduringtheimplementationoftheproject,andtakecorrectiveactionswhentheprojectobjectivesd
5、eviate.Applicationof2Z101042masterdynamiccontrolmethodinconstructionmanagement(P30~31)1.usedynamiccontrolprincipletocontrolconstructionscheduleProceduresforthedynamiccontroloftheprocesswiththeaforementionedprojectobjectivesTheschedulecontrolcycleshouldbedeterminedaccordingtothesizeandcharacteri
6、sticsoftheproject.Thegeneralprojectcontrolcycleisonemonth.Forimportantprojects,thecontrolcyclecanbedefinedastendaysoroneweek.Comparisonoftheconstructionprogressoftheprojectvalueandtheactualvalueshouldbepaidattentionto,thecorrespondingcontentsoftheprojectshouldbeconsistent,suchasthemilepostevent
7、progresstargetvalueorfurtherprogressofthetargetvalueastheprogressoftheplanistheprogressofthevalue,theactualvalueisrelativetothemileposteventorthenrefinetheworkintotheactualprogress.2.usedynamiccontrolprincipletocontrolconstruction