《毕业设计灯泡贯流式机组座环安装设计》由会员上传分享,免费在线阅读,更多相关内容在行业资料-天天文库。
1、三明职业技术学院毕业作业作业形式:毕业设计作业题目:灯泡贯流式机组座环安装设计完成日期:2013年5月12日摘要本安装设计方案中阐述了座环内外环,上下导流板的安装流程,以及座环主要部件的翻身及吊装,拼装后座环焊缝的焊接工艺,整个安装过程中,保证其座环的水平度至关重要.座环的水平精度高,才能使组装好的机组旋转轴线始终保持垂直状态关键词:座环内环、导流板、支撑管、焊接、水平度。目录第一章贯流式机组概述···········································4页1.1座环主要的安装数据设计参数···········
2、······················4页1.2座环主要的技术参数·········································4页第二章质量要求··················································5页2.1规范要求···················································5页2.2设计图纸要求···············································5页2.3质量控制措施·······
3、········································6页第三章施工条件··················································6页3.1现场、技术准备·············································6页第四章水轮发电机组座环的施工流程·································7页第五章座环的倒运和吊装··········································8页5.1座环主要部
4、件的二次倒运、吊装·······························8页5.2座环内外环上、下半部的翻身及吊装··························13页第六章座环焊缝的焊接工艺·······································14页6.1座环重要焊缝的焊接工艺····································14页6.2焊接前准备工作············································14页6.3焊接工艺过程·········
5、·····································15页第七章施工步骤·················································18页7.1基准控制点放样及安装数据测量······························18页7.2座环内环与支柱组装、焊接··································19页7.3座环安装··················································25页第八章座环另增设的加固
6、措施·····································26页第九章安全措施·················································27页第十章主要工器具、劳动力·······································28页结束语··························································29页参考文献·················································
7、·······29页第一章贯流式机组概述本安装设计方案适用于由东方电机有限公司制造的水轮发电机组的机组座环的拼装、倒运、吊装、安装。座环的部件包括:座环内环(2/2),座环上/下支柱,座环上支柱坑衬,座环外环(4/4),座环外环后段(4/4),上/下导流板,上游里衬(4/4),座环外部支撑(2个),座环下游支撑管,座环内部支撑等。工地需完成座环的拼(组)装、焊接、整体安装调整、焊缝检查,同时安装座环所需要的锚具、内外支撑。1.1座环主要的安装数据设计参数:1)、座环下支柱垫板预埋高程12.3m2)、机组中心线高程22.8m3)、下支柱底部
8、高程12.34m4)、上支柱顶部高程33.68m5)、转轮中心线的设计横坐标0+047.7m6)、机组轴线的设计纵坐标0+616.7m7)、座环外环法兰面的设计横坐标0+044.0m8)、座环