《重庆某轻轨高架车站施工组织设计(清水混凝土)-典尚设计-三维动画效果图.doc》由会员上传分享,免费在线阅读,更多相关内容在学术论文-天天文库。
1、编制依据1.《重庆市****轻轨站工程建筑、结构、安装设计图纸》(2009年6月、B版)2.《建设工程项目管理规范》GB/50326-20013.《建筑工程清水混凝土施工技术规范》(DB11/T464-2007)4.《混凝土外加剂应用技术规程》(DBJ01-61-2002)5.《建筑地基基础工程施工质量验收规范》GB50202-20026.《普通混凝土配合比设计规程》(JGJ55-2000)7.《工程测量规范》GB50026-968.《混凝土结构工程施工质量验收规范》GB50204-20029.《砌体工程施工质量验收规范》GB50203-200210.《建筑装饰装修
2、工程质量验收规范》GB50210-200111.《建筑给水排水及采暖工程施工质量验收规范》GB50242-200212.《建筑电气工程施工质量验收规范》GB50303-200213.《钢筋机械连接通用技术规程》JGJ107-9614.《钢筋焊接及验收规范》JGJ18-200115.《建筑施工扣件式钢管脚手架安全技术规范》JGJ130-200116.《西南地区现行建筑标准设计通用图》17.《建筑工程大模板技术规程》(JGJ74-2003)18.《混凝土结构施工图平面整体表示方法制图规则和构造详图》(03G101)87目录编制依据····················
3、·····································2第一章工程概况···················································41、工程建设基本概况··················································42、工程地质及自然条件概述···········································43、工程设计概况······················································54、现场施工条件
4、······················································55、主要分部分项工程量·················································56、工程特点、难点、重点···············································6第二章施工组织与部署················································71、管理目标·············································
5、·············72、施工组织机构·······················································73、施工部署···························································9第三章施工准备及资源配置计划········································111、施工准备···························································122、各种资源配置计划·········
6、··········································12第四章87施工进度计划··················································141、总工期····························································142、施工各节点计划及说明··············································143、工期保证措施············································
7、···········14第五章施工平面布置·················································151、平面布置原则······················································152、现场平面布置及说明·················································153、现场布置图·························································16第六章主要施工方案··········