《商南县金福湾21#楼施工进度计划表》由会员上传分享,免费在线阅读,更多相关内容在教育资源-天天文库。
1、施工进度总计划(横道图)序号施工部位工期(d)起止时间10.1511.1512.152012.1.152.153.154.155.156.157.158.159.1510.1511.1512.152013.1.152.153.154.155.156.173060901201501802102402703003303603904204504805105405706006251施工准备410.1~10.32土方开挖1010.4~10.143垫层回填510.15~10.204测量放线110.20~10.215C15砼垫层110.21~10.226基础防水施
2、工210.23~10.247地下室结构4510.25~12.108外墙防水312.10~12.139土方回填712.13~12.163序号施工部位工期(d)起止时间10.1511.1512.152012.1.152.153.154.155.156.157.158.159.1510.1511.1512.152013.1.152.153.154.155.156.17306090120150180210240270300330360390420450480510540570600625103层以下框架结构4012.14~2012.1.17113~6层框架主
3、体452.8~4.24126层以上框架904.24~7.20133层以下砌体307.14~8.14143~6层砌体308.14~9.13156层以上砌体1009.14~12.2516室内找平层1189.2~12.303序号施工部位工期(d)起止时间10.1511.1512.152012.1.152.153.154.155.156.157.158.159.1510.1511.1512.152013.1.152.153.154.155.156.17306090120150180210240270300330360390420450480510540570
4、60062517屋面工程6510.2~12.518外墙工程4011.6~12.1519室内工程10311.26~2013.5.720室外台阶散水等152013.5.8~5.2321水电安装3107.20~2013.6.122交工验收106.7~6.171、本工程工期为625天,从2011年9月15日~2013年6月17日。2、本进度计划是在其他工种预留预埋及时的前提下排定的.3、未考虑重大设计变更及不可抗拒因素对工期的影响。3