资源描述:
《运动场排水沟施工技术标(1)》由会员上传分享,免费在线阅读,更多相关内容在行业资料-天天文库。
1、第一章工程概况一、工程建设概况新疆师范大学附中文光校区田径运动场给排水工程,位于新疆师范大学附属中学文光校区内,为田径运动场基建改造维修工程。随着校区发展的要求,本工程建设已迫在眉睫。工期要求:接到甲方开工令后在30个日历日内竣工。二、建筑设计特点本工程建筑施工均按照国家及自治区建筑工程施工统一技术规范及施工操作规程施工。三、结构设计特点1、排水沟:内圈排水沟采用钢筋混凝土沟体,上盖预制盖板排水沟变形缝每30M设一道,设在盖板板缝处。排水沟的出口接入附近排水渠内,坡度3%排水沟给水管为PPR塑铝稳态管,
2、埋地给水管为PE塑料管,雨水管采用直埋机制柔性铸铁管2、检查井做法:给水阀门井做法按新02S2第六页,井盖采用复合材料检查井盖。排水检查井采用Ф1250园形砌块检查井,井盖用轻型铸铁井盖,直径700.povertyalleviation,makingstablepovertyofvillageandexitinatimelymanner,shouldsupportpovertyalleviationinto,fromthe...Thestabilityoffamilies,notsimplyoneoff
3、,notonlyto"helpahorse",and"givingalift"topreventpovertyandreturningagain.(D)toco-ordinatetheconfigurationresourceforpovertyalleviation.Onehandtoworkactivelytowardsasuperiorpolicy.CentralworkConferenceofpoverty-alleviation,CentralGovernmentofGeneraltransf
4、erpayments,varioustypesofspecialtransferpaymentsinvolvingthepeople'slivelihood,inordertofurthertopoorareas.NationalRevolutionarydevelopmentseminarspresented"fivecloselyaroundthe",developedtosupportdevelopmentandconstructionofoldrevolutionaryviews.PrimeMi
5、nisterLikeqiangontheCPPCCwasspecificallyproposedintheGovernmentworkreport:"nationalwastemanagementpoliciesandthepeople'slivelihoodprojectstoimpoverishedareas."Meanwhile,provincesandcitieswillalsobesupportingtheintroductionofappropriatepolicies.Thesepolic
6、iesisverylarge,the......Forcountiesnotonlyopportunitiesforpovertyeradication,itiscatchingup,promotethedevelopmentofopportunitiesinthesurroundingarea.Departmentsatalllevelsmustfirmlygraspthisgoldenopportunity,lettheseopportunitiesbecomecrucialforpovertyer
7、adicationnotonlyapowerfullever,alsobecame......Powerfulbreakthroughtooveralldevelopment,withovertaking.Otherintegration-relatedfunds.Atthemeeting,"twooffices"introducedtheintegrationofagriculture-relatedprojectsfundsgivingprioritytopoorimplementationofvi
8、llage-poortilt,clearintegrationofthe4majorcategoriesoffundsanduseoftheprocess.Theinvolveddepartments,undertheunifiedcommandoftheleadinggroupofpovertyalleviationanddevelopmentintheCounty,四、工程施工特点1、工期紧,根据招标文件,本工程总工期仅有30天,但我公