《基槽挖土签证》由会员上传分享,免费在线阅读,更多相关内容在工程资料-天天文库。
1、一、基槽挖土:24.5×104.32×2.043=5221.58m3二、电梯井挖土:11.9×5.6×1.9×5=633.08m3三、塔吊基础挖土:8×7×4.2=235.2m38×7×2.2=123.2m3四、地基超挖:(12.35-10.35)×6×5=60m33×4×0.6=7.2m34×11.5÷2×1.15=26.45m3(12×14.5-6×5)×(11.5-10.35)=165.8m37×8×(10.75-10.35)=22.4m33×6×(11.85-10.35)=27m37×6×(10.75-10.35)=16.8m33×5×(10
2、.8-10.35)=6.75m3〔7.2×1.5×2.4+6.4×0.9×1.4+6×(1.5+2.5)÷2×(1.5+0.9)÷2〕×5=241.92m39.2×1.4×2.043×2=52.627m3合计:6840.007m3马镫钢筋:Φ22(21.6+26.4)×53×2.98628÷1000=7.5274tΦ168.26×53×1.57952÷1000=0.6914tΦ122.4×53×0.88848÷1000=0.1128t基础筏板绑扎搭接钢筋:东西向钢筋Φ22:100×15.4×2×2.98628÷1000=9.197t南北向钢筋Φ22:
3、235×5.5×2×2.98628÷1000=7.72t电梯井钢筋Φ22:35×5×2.98628÷1000=0.523t合计:Φ22:24.97tΦ16:0.6914tΦ12:0.1128t地基超挖回填毛石砼:(12.35-10.35)×6×5=60m33×4×0.6=7.2m34×11.5÷2×1.15=26.45m3(12×14.5-6×5)×(11.5-10.35)=165.8m37×8×(10.75-10.35)=22.4m33×6×(11.85-10.35)=27m37×6×(10.75-10.35)=16.8m33×5×(10.8-10
4、.35)=6.75m3〔7.2×1.5×2.4+6.4×0.9×1.4+6×(1.5+2.5)÷2×(1.5+0.9)÷2〕×5=241.92m39.2×1.4×2.043×2=52.627m3合计:626.959.2×1.4×2.043×2=52.627m3m3禁止吸烟谢谢合作